BRIGHTER LIGHTS?

"Notice how the lights now seem brighter?"

A joke, of course, but Hoyt may have correctly put his finger on the future dependability of the Island's power source.

As of 1:00 p.m. Friday, Lee Engstrom reported, the Island's power shifted from the old submarine cable to the new cable, and without a hitch.  Both men serve as directors of the REA Board, and they, as well as Manager Robert Cornell and other REA crew and Directors, should feel both relieved and proud of this accomplishment.  Lee accompanied contractors daily during cable repair and cable laying activities in order to properly document with photos this past year's events.

Monday, Feb. 4, Wisconsin Public Service crew spliced
new cable, connecting both old and new supply cables 
to this switch box, and to the line that runs underground,
leading to theElectric Co-op sub-station. 
 Lee Engstrom is at right, with camera.


Problems began with the unanticipated underwater cable failure in June, and the need to repair that break as quickly as possible.  This initiated multiple steps in logistics and timing:  underwater divers; a cable splicing crew; a work barge with tug to lift and cut the failed section and then reset the repaired cable back in place.

In the fall of 1980, cable arrived on a barge, but so had
winter, and it would be spring before weather permitted
laying the first underwater electric cable for the Island.


The checklist was long, the cost was unexpected, and the long-term outlook, given the old cable's status, remained one of uncertainty.

That cable had been laid in spring of 1981, but given the low draw compared to its rated capacity, and given exclusive use in fresh water, expectations were for it to have a longer life span.  However, along the relatively flat rock bottom west of Plum Island, and at a depth of 40 feet, ice nevertheless had shoved and abraded the cable over time.  Fortunately, this break resulting in an instant power outage on the Island occurred at the start of our summer and in warmer weather.  This made cable location and repair easier than if it had been mid-winter.  Generators were then started and placed on line, but at a significant cost in daily fuel consumption.  An emergency CAT generator had to be located and trucked to the Island when one of the two REA units suffered failure of an air intake casting. This series of events even further compounded the main cable repair challenge and stretched limited resources of the Co-op team.

Almost as soon as cable failure occurred and simultaneous with the on-going repairs that would stretch to ten days' time, the REA's plan of action was exercised, led by the Electric Co-op's manager, Robert Cornell.   It called for the procurement of a new cable, to be manufactured by an east coast firm.  It would be of length based on a new route, different from that previously used.  Rather than route the cable around Plum Island as was previously done, a route that might once again subject the cable to shoving ice fields, this time the cable would be laid inside a polyethylene sleeve and trenched to at least 20-foot depth, and it would run from Northport to Plum Island.  Then the cable would cross Plum Island underground, using less expensive, land-based cable material trenched in soil.  Near the old Plum Island Life Saving Station it would reenter the lake and from there cross to Washington Island. It would come ashore alongside the 1981 electric cable, in an easement adjacent to the former Goodwin Berquist property.  Now, a new switch box links both old and new underwater cables to terminals that can connect to the underground cable leading inland to the REA distribution center, on Main Road.

Island lineman Mike Jorgenson with Public Service splicing
crew, Feb. 4.   New switch box shown.  Ferry Arni J. Richter
is a dot near the horizon, background. 


Like any large project, timing is everything:  to obtain needed cable from manufacturer before freeze up, when ice covers the lake and makes waterborne construction impossible; trenches dug from shore into the water at four locations, with a ten-inch polyethylene sleeve buried and ready to accept the cable at each entry point; and also, to lay the Plum Island segment of underground cable while landing there with men and equipment was still easily managed.

The new cable arrived by truck in Sturgeon Bay, later than expected and promised, on enormous reels.  It was loaded on contractor Roen's work barge at Bay Shipbuilding.  This delay in cable delivery pushed back laying new cable until the middle of December.  But then, by good fortune, a series of windless, warm days permitted the Roen crew to successfully lay the two segments of underwater cable.  Only a few hundred feet of surplus remained on either side of the runs, in the event of course deviation while tug and barge laid cable.

A separate company monitored the laying of the cable with underwater cameras to assure the new electric cable did not pass over large, sharp rocks, or suspend, unsupported, over wide crevices.

Dec. 15 - A brief return of warm weather and light air enabled Roen 
Construction to lay the two underwater cable sections without a hitch. 
Divers connected cable ends to a loom attached to a heavy wire rope, 
then helped feed the end into the conduit as it was pulled ashore 
through the sleeve by Tom Jordan's excavator.


The splicing of cable segments to one another, and to the Wisconsin Public Service feed at Northport, was completed, then, this past week, with the new cable becoming "live" early Friday afternoon.   The old cable remains energized, just in case, under a greatly reduced load, in order to remain dry and usable.

  Sections of plastic conduit were bolted together into approx. 
500-ft. lengths and laid out on the Potato Dock prior to being 
towed into position and sunk into trenches dug at each exit/entry point.  
Red conduit is for fiber-optic cable. (Taken in early December.)



Congratulations on a major effort, a "well done" to all involved.

Now, what about the fiber optic cable laid alongside the new electrical cable?  It's caused Co-op manager Robert Cornell the least concern, up until now.   As this project winds up (some back-filling still necessary where the cable enters/exits near shore at Northport) it, too, will get attention.

 -  Dick Purinton

















Wednesday, May 1, 2013

DREDGING DANCE WORKED!

Long underwear and patience were the order of the day 
back in early March when Mike Kahr's barge returned to Detroit Harbor to 
dredge near the island docks.   Hoyt Purinton will be in short sleeves, and smiling, 
when he sees the Roen Company construction barge
enter port later this summer.
Detroit Harbor, Washington Island -

There was never a certainty, but quiet optimism prevailed until the moment when the Wisconsin Legislature's Joint Finance Committee approved a measure yesterday in the state's budget bill for $5.2 million to dredge the Detroit Harbor channel.  This is believed to be the most difficult hurdle to funding the channel dredging project.

Rep. Garey Bies said, “This is great news for the residents of Washington Island.   I’m thankful to the members of the committee who listened to my concerns and prioritized funding for the project."

Bies also commented on the potential economic loss should the channel impede regular ferry transit:

"While the safety of the residents of the Island is the biggest concern, I was also worried about the significant economic impact a loss of ferry access would mean to the Island and our district as a whole. Year-round access generates more than $16 million in annual economic activity through the transportation of passengers, vehicles and cargo." 

This is about the best news we've had in this corner of Lake Michigan since an effort was begun in August of 2007 to gain the attention of government officials. At that time, beginning with an historic, in-person visit by then sitting Senator Russel Feingold, the project was posed but water levels weren't as extreme as they soon became during late 2012.   Several meetings attended by local, state and federal officials brought sympathy for our situation, and behind-the-scenes conversations took place, but the effort didn't seem to be of a serious nature until work with the Wisconsin Department of Transportation's Harbor Assistance Program (HAP) began in 2011.

Last June, as you may recall, Washington Island's 2012 HAP grant was turned down, and for several good reasons.  Efforts were made to provide better engineering data, and this was augmented by a Wisconsin HAP grant for approximately $150,000 late in 2012.  Bottom core samples, exacting yardage fignure - in short, a project ready for bids, resulted from that grant, and it culminated in three contractor bids for the actual project last month.  While no official selection has been made, the Roen Salvage Company of Sturgeon Bay was low bidder and is expected to be awarded the contract once the HAP funds are officially secured.   The $5.2 million figure represented the combined total of the Roen bid, plus engineering fees, plus contingency, plus anticipated island road repair costs from heavy truck traffic.

The Joint Finance Committee's vote (12 to 4) won't be the final hurdle.   Action is still needed in the State Senate and Assembly, with the governor's signature after that.    The earliest possible formal, final approval would take place in late June as the state's two-year budget is approved.

The significance of this recent action, put forward by our State Senator Frank Lasee and his staff members, and Garey Bies and his staff on behalf of Washington Island, is that the money is marked for Detroit Harbor.   Other ports will have a chance to apply for other available money in the HAP grant pool, but Washington Island's project has been underscored as being essential and not to be upstaged by other needed commercial port work.

Thanks through email, phone call or letter is due Senator Lasee, Rep. Bies for their legislative work, and to members of the Town of Washington Board who stuck with the HAP program application process through a second round.   
Contact information for Rep. Garey Bies:  
         Toll free phone:   888482-0001     or email:       Rep.Bies@legis.state.wi.us
                     P.O. Box 8952    Madison, Wisconsin   53718-8952
State Senator Frank Lasee's contact information:  
         Phone:   608-266-3512                       email:      Sen.Lasee@legis.wisconsin.gov        
                       State Capitol Rm. 3165, P.O. Box 7882, Madison, Wisconsin  53708

Town Chairman Joel Gunnlaugsson took
the call with the good news from Rep. Garey Bies at the Northport
pier late Tuesday afternoon.
Other good news coupled with this extraordinary legislative action for Washington Island is that Lake Michigan's level continues to rise slightly each week.   In yesterday's brisk, southerly breeze, water levels were at their highest since sometime in early August of 2012.

-   Dick Purinton